AIR QUALITY/ hazardous materials/ ABATEMENT
April 8, 2016
The Miller-Driscoll Building Committee has approved an adjustment to the project's construction schedule and phasing, resulting in a new projected completion date of Labor Day 2017, in time for the start of the 2017-2018 school year and 3+ months ahead of the current schedule. Abatement activity will be included in these changes.
All abatement will be performed when school is not in session (during summer and holiday breaks while the renovation is underway), and will be followed by the renovation of that same area. Students will reoccupy the space only after the renovation of that area is complete, which will be weeks or months after the abatement activity has occurred.
The Miller-Driscoll Building Committee has approved an adjustment to the project's construction schedule and phasing, resulting in a new projected completion date of Labor Day 2017, in time for the start of the 2017-2018 school year and 3+ months ahead of the current schedule. Abatement activity will be included in these changes.
All abatement will be performed when school is not in session (during summer and holiday breaks while the renovation is underway), and will be followed by the renovation of that same area. Students will reoccupy the space only after the renovation of that area is complete, which will be weeks or months after the abatement activity has occurred.
OVERVIEW
Hazardous building materials investigation summary, Abatement specification, SIP, Abatement process, October 12, 2015
Hazardous building materials investigation summary, Abatement specification, SIP, Abatement process, October 12, 2015

trc_report_-_2015-10-12_md_hazmat_overall_summary.pdf | |
File Size: | 301 kb |
File Type: |
Design Review, Hazardous Materials Investigation Summary & Abatement Process (p. 8-17), Construction Phasing presentation to Miller-Driscoll parents, neighbors and Wilton community, October 14, 2015

presentation_-_2015-10-14_design_review_hazmat_investigation_summary_abatement_process_construction_phasing.pptx | |
File Size: | 6517 kb |
File Type: | pptx |
ABATEMENT / TESTING /SURVEY REPORTS & NOTICES
TRC, an environmental consulting firm, is managing the investigation and abatement of hazardous materials at the Miller-Driscoll building site.
ATC Associates, an environmental consulting firm, conducted work for the forensic evaluation of the Miller-Driscoll buildings in 2012 as well as three year inspections and asbestos management update in 2015 .
TRC, an environmental consulting firm, is managing the investigation and abatement of hazardous materials at the Miller-Driscoll building site.
ATC Associates, an environmental consulting firm, conducted work for the forensic evaluation of the Miller-Driscoll buildings in 2012 as well as three year inspections and asbestos management update in 2015 .
April 16, 2017 - Indoor air sampling Apr 14

trc_report_-_2017-04-14_indoor_air_sampling.pdf | |
File Size: | 551 kb |
File Type: |

trc_report_-_2017-04-14_esml_indoor_air_sampling.pdf | |
File Size: | 116 kb |
File Type: |
December 31, 2016 - Indoor air sampling Dec 23, 24 26-29, 31

trc_report_-_2016-12-31_indoor_air_sampling_dec_23_24_26-29_31.pdf | |
File Size: | 3048 kb |
File Type: |
December 18, 2016 - Indoor air sampling Dec 16, 17

trc_report_-_2016-12-18_indoor_air_sampling_dec_16_17.pdf | |
File Size: | 9758 kb |
File Type: |
December 11, 2016 - Indoor air sampling Dec 10, 11

trc_report_-_2016-12-11_indoor_air_sampling_dec_10_11.pdf | |
File Size: | 14457 kb |
File Type: |
December 4, 2016 - Indoor air sampling Dec 3

trc_report_-_2016-12-04_indoor_air_sampling_dec_3.pdf | |
File Size: | 7628 kb |
File Type: |
November 27, 2016 - Indoor air sampling Nov 23, 25, 26

trc_report_-_2016-11-27_indoor_air_sampling_nov_23_25_26.pdf | |
File Size: | 4074 kb |
File Type: |
November 21, 2016 - Notice of Abatement in unoccupied construction area during holiday weekend

md_abatement_notice_2016-11-21.docx | |
File Size: | 12 kb |
File Type: | docx |
November 11, 2016 - New Addition IAQ Nov 7, Nov 9, Nov 11

trc_report_-_2016-11-11_new_addition_indoor_air_sampling_nov_7_nov_9_nov_11.pdf | |
File Size: | 8097 kb |
File Type: |
September 1, 2016 - Miller IAQ Aug 29 & Sep 1

trc_report_-_2016-09-01_miller_indoor_air_aug_29_sep_1.pdf | |
File Size: | 10634 kb |
File Type: |
August 31, 2016 - Miller-Driscoll abatement & testing Jun 15-Aug 22

trc_report_-_2016-08-31_miller_driscoll_hazmat_activities_june_15-august_22.pdf | |
File Size: | 14977 kb |
File Type: |
August 29, 2016 - Driscoll IAQ Aug 25

trc_report_-_2016-08-29_driscoll_indoor_air_august_25.pdf | |
File Size: | 11900 kb |
File Type: |
May 13, 2016 - Caulking/glazings/building substrates sampling for PCBs Apr 12, 14, 15

trc_report_-_2016-05-13_caulk_glazing_building_substrates_sampling.pdf | |
File Size: | 8674 kb |
File Type: |
February 26, 2016 - Abatement Feb 20

trc_report_-_2016-02-26_hazardous_materials_oversight_february_20.pdf | |
File Size: | 3580 kb |
File Type: |
February 18, 2016 - Abatement Feb 10-15

trc_report_-_2016-02-18_hazardous_materials_oversight_february_break.pdf | |
File Size: | 3700 kb |
File Type: |
February 15, 2016 - Safe to reoccupy notice

trc_letter_-_2016-02-15_safe_to_reoccupy_school.pdf | |
File Size: | 134 kb |
File Type: |
January 22, 2016 - Lead in air analysis

trc_report_-_2016-01-22_lead_in_air_analysis.pdf | |
File Size: | 6920 kb |
File Type: |
December 1, 2015 - December break abatement

trc_report_-_2016-01-12_hazardous_materials_oversight_holiday_break.pdf | |
File Size: | 921 kb |
File Type: |
December 11, 2015 - Temporary classrooms follow up indoor air sampling

trc_report_-_2015-12-11_temporary_classrooms_follow_up_indoor_air_sampling.pdf | |
File Size: | 371 kb |
File Type: |
December 11, 2015 - Pre-construction baseline air sampling

trc_report_-_2015-12-11_pre-construction_baseline_air_sampling.pdf | |
File Size: | 394 kb |
File Type: |
December 2, 2015 - Temporary classroom indoor air sampling

trc_report_-_2015-12-02_temporary_classrooms_indoor_air_sampling.pdf | |
File Size: | 498 kb |
File Type: |
July 2015 - Pre-demolition/renovation investigative survey for hazardous building materials Miller Driscoll Elementary School

trc_md_school_hazbuildingmaterials_inspection_survey_final_rev._07-13-15.pdf | |
File Size: | 19983 kb |
File Type: |
May 4, 2015 - Focused soil investigation

trc_report_-_2015-5-4_focused_soil_investigation.pdf | |
File Size: | 2922 kb |
File Type: |
April 28, 2014 - Full IAQ

trc_report_-_2014-04-28_trc_md_full_iaq_report.pdf | |
File Size: | 5918 kb |
File Type: |
April 28, 2014 - Radon

trc_report_-_2014-04-28_trc_md_radon_testing.pdf | |
File Size: | 6347 kb |
File Type: |
April 15, 2014 - Radon & IAQ

trc_report_-_2014-04-15_trc_md_radon_and_iaq_report.pdf | |
File Size: | 100 kb |
File Type: |
August 2012 - Microbial and indoor environmental quality assessment

atc_associates_2012-08_microbial___indoor_environmental_quality_assessment.pdf | |
File Size: | 5983 kb |
File Type: |
August 2012 - Survey to identify asbestos-containing materials

atc_associates_2012-08_survey_to_identify_asbestos_containing_materials.pdf | |
File Size: | 8572 kb |
File Type: |
CONFORMANCE SPECS
Asbestos abatement

section_028213_asbestos_abatement.pdf | |
File Size: | 370 kb |
File Type: |
Lead hazard control activities

section_028313_lead_paint_activity.pdf | |
File Size: | 381 kb |
File Type: |
Removal and disposal of PCBs

section_028433_pcb_abatement.pdf | |
File Size: | 352 kb |
File Type: |
Removal and disposal of PCB contaminated soil

section_026123_pcb_soil_removal.pdf | |
File Size: | 267 kb |
File Type: |
Transport and disposal of hazardous materials

section_028100_hazmat_handling.pdf | |
File Size: | 282 kb |
File Type: |
DOCUMENTS FOR KOHLER
Documents and information requested by the Kohler family regarding the abatement of hazardous materials at Miller-Driscoll.
Documents and information requested by the Kohler family regarding the abatement of hazardous materials at Miller-Driscoll.
ENVIRONMENTAL SITE ASSESSMENT

trc_final_m-d_school_phase_i_esa_report_03-17-2015.pdf | |
File Size: | 20299 kb |
File Type: |
LEGAL INVOICES
Shipman and Goodwin October 2014 - November 2015

shipman_and_goodwin_10-14_to_11-15.pdf | |
File Size: | 1432 kb |
File Type: |
MANAGEMENT
Driscoll three-year inspection and asbestos management plan update

atc_driscoll_asbestos_management_report_2015.pdf | |
File Size: | 8620 kb |
File Type: |
Miller three-year inspection and asbestos management plan update

atc_miller_asbestos_management_report_2015.pdf | |
File Size: | 9845 kb |
File Type: |
Self-implementation cleanup plan

trc_-_2015-05-22_md_sip.pdf | |
File Size: | 23647 kb |
File Type: |
PROPOSALS
Proposal for pre-construction baseline air sampling
Proposal for pre-construction baseline air sampling

trc_proposal_-_2015-12-01_pre-construction_baseline_air_sampling.pdf | |
File Size: | 875 kb |
File Type: |